NETRACON Technologies performed numerous jobs for construction of 380kV Overhead Transmission lines in KSA for Al Sharif Group and KEC Ltd. Co. from January 2015 to April 2017. The scope includes Erection of Towers, Stringing of Conductor and OPGW as per following details:
380kV, 132kV and 110kV, Overhead Transmission Lines, Saudi Arabia
JOBS EXECUTED IN KINGDOM OF SAUDIA ARABIA - NETRACON Technologies performed numerous jobs for construction of 380kV Overhead Transmission lines in KSA for Al Sharif Group and KEC Ltd. Co. from January 2015 to April 2017.
- M409 – 380kV OHTL associated with TAIF East Governorates 380-110kV BSP (WOA):
- Complete Tower Erection:
- 355 Towers
- Complete Stringing of AAAC Conductor:
- 81 Km
- Complete Stringing of OPGW:
- 56 Km
- M410 – Installation of 110kV Double Circuit OHTL for Al Khurmah & Al Mowayh SS Taif:
- Complete Tower Erection:
- 205 Towers
- Complete Stringing of AAAC Conductor:
- 36 Km
- Complete Stringing of OPGW:
- 36 Km
- M605 – Connection of Al-Shabayn 132/33kV Substation in Tihama with Network:
- Complete Stringing of ACSR Conductor:
- 17 km
- Complete Stringing of OPGW:
- 17 Km
- M510 – Construction of 380kV OHTL from Jazan Refinery P-P to Muhayil West 380kV BSP:
- Complete Stringing of ACSR Conductor:
- 17 km
- Complete Stringing of OPGW:
- 06 Km
- M411 – 380kV OHTL from RPG IPP2 to MHR and from RBG3 to RBG-IPP2 including GIL SS. Tower Erection – 4 nos. including one Special Tower (100m High Weighing 103 Ton) on the top of very steep Mountains in Arafat area.