330kV Transmission Lines, Ghana, Africa

330kV Transmission Lines, Ghana, Africa

Scope:
  • Erection of Towers & Stringing of 330 kV Single Circuit (130.241 km) and Double Circuit (14.834 km) and stringing of 1 No. 24 Fiber OPGW (144.817 km) of 330 kV T/Line from Volta – Tornu

Date of Start: 5h April 2013

Date of Completion: 25th Oct 2014

  • Erection of Towers & Stringing of 330kV Single circuit, two conductors per phase, ACSR Tern Conductor and 1 No. Alumoweld Shield wire & stringing of 1 No. 24 Fiber OPGW of 330 kV T/Line Aboadze Thermal Plant to Volta SS Tema, Ghana – Africa.

Date of Start: 24h Nov 2008

Date of Completion: 30th Dec 2009

Client: VRA / KEC Int’l

Project Completion Certificate

ASK US