220/20kV Substation, Ghazni, Afghanistan

220/20kV Substation, Ghazni, Afghanistan

Construction of 220kV Ghazni Substation was executed on behalf of KEC Int’l (DABS 92-ICB-004). The following facilities were developed under the project:

  • Site improvement by Developing a Steep Hilly site into terraces by constructing 2.5 KM long RCC/Stone Masonry (Av: 4 M high) Retaining walls. 1.6 Km long Boundary Wall & 0.96 Km long Switchyard Fence
  • Construction of Control Hosue Building, Equipment Foundations, 758 M long Cable Trenches, Walk Ways (1.6 Km long) & 3.33 Km long Drainage system lines.
  • Provision of HVAC, Indoor/Outdoor Lighting System, Fire Fighting along with Fire Alarm arrangements.
  • Installation of Four (4) Line Bays (CTs / VTs / CBs / Line Disconnectors / Bus Disconnectors)
  • Installation of Three (3) Trafo Bays (CTs / VTs / CBs / Line Disconnectors / Bus Disconnectors)
  • Installation of Three (3) Transformers 10/13 MVA
  • Testing and commissioning of all High Voltage Equipment and the Overhead Busbar system
  • Installation, testing, and commissioning of MV Switchgear – 20 KV (2 + 17), Station Auxiliary 
AC/DC supply systems
  • Installation, testing, and commissioning of Control & Protection System
  • Installation, testing, and commissioning of Substation Automation System.
  • Installation, testing, and commissioning Telecom and RTU

Date of Energization: 19th September 2017

Project Completion Certificate

ASK US