Welcome to Netracon Technologies!

Introduction

NETRACON Technologies is a well-known formation in the field of Power Transmission

in the region. NETRACON has ample expertise of working in various area, terrain,

regions & countries. NETRACON has successfully completed projects in Malaysia,

Philippines, Ethiopia, Ghana, Cameroun, Saudi Arabia, & Tajikistan besides Afghanistan

& Pakistan as sub-contractor as well as EPC contractor.

NETRACON Technologies is registered with PEC (Category: CA – No Limit) along with

ISO certification as EN ISO 14001 2004, EN ISO 90012008 & OHSAS 18001 2007

In Afghanistan, NETRACON has completed Five (5) 220 kV Grid Stations & Six (6) 110

kV Grid Stations besides completing more than 600kM long 220 kV Transmission Lines

& 157 Km long 110 KV T/Lines besides SCADA phase-1.

In Tajikistan, NETRACON have completed one 500 kV GIS & one 220 kV GIS for

ALSTOM (now GE).

In Pakistan, NETRACON Technologies has completed the EPC works of two 500KV and

two 220KV Transmission Lines,132 kV Switchyard Layyah for Thal Power, besides

completing 132 kV switchyards of 175 MW ALMOR Bhikki & Satpara Hydro power

NETRACON was responsible for designing & construction of civil works, Installation,

Testing & Commission of six (6) 132 kV Grid Stations in Karachi and Eleven (11) 132 KV

Grid Stations in GEPCO including two GIS for GEPCO and upgrade Palandari (AJK)

Grid station from 33 kV to 132 kV Under IESCO.

NETRACON Technologies was responsible for designing & construction of civil works,

Installation, Testing & Commission of SVC for ABB at 220 kV Kotlakhpat GS, Lahore, the

only project of its type in Pakistan.

Recently NETRACON Technologies has completed 209 KM Long Golengol –Chakdarah

T/Line (crossing 3500 M altitudes of Lowaree) Project including 132 kV Chitral Grid

Station, Timergara Ext & Chakdra G/S Ext. as EPC Contractor. Besides, NETRACON

have constructed 220 kV Mansehra Grid Station as well as 132KV Grid Station in Piplan

near Mianwali.

 

 

NETRACON Technologies has the most experienced team in Primary & Secondary

design of Grid Stations.

NETRACON Technologies owns its own fleet of transport, Construction Machinery,

Excavators, Concrete Batching Plant, Cranes, Dehydration Plants, Testing Equipment &

trained Human resources (+900 Employees) List Attached.

NETRACON is known for quality performance & timely delivery of the projects.

NETRACON has never been levied any LD in its 20 years’ history of performance across

the globe.

Projects

ADB (105) Procurement of Plant – Design, Supply, Installation, Testing and Commissioning of Lot I: 500kV Double Circuit Q/B Transmission Line for Looping In & Out of existing 500kV Multan Gatti Single Circuit Transmission Line at 500kV Faisalabad West Substation

Project Detail

Procurement of Plant – Design, Supply, Installation, Testing and Commissioning of         Lot I: 500kV Double Circuit Q/B Transmission Line for Looping In & Out of existing 500kVMultan Gatti Single Circuit Transmission Line at 500kV Faisalabad West Substation

(approx.40 km—Drake Conductor)

Time Period

05 Nov 2015 ~ 30 Jun 2018

Location

Pansra area near Faisalabad,  Punjab , Pakistan

Award Date

Sept 17, 2018

Effective Date

Feb 01, 2019

Expected Completion

Jan 31, 2020

Client

National Transmission Dispatch Company Limited (NTDC)

Status

30% Complete

Read Complete Report

ADB-103: Procurement of Plant - Design, Manufacturing, Supply, Installation, Testing & Commissioning of Protection Relays, Fault Recorders, Fault Locators and Event Recorders of NTDC system in South Area..

Project Detail

Design, Manufacturing, Supply, Installation, Testing & Commissioning of Protection Relays, Fault Recorders, Fault Locators, and Event recorders of NTDC system in South Area

Award Date

 Aug 31, 2018

Location

The Project Sites are in 11 different Grid Stations in South Area of Sindh and Balochistan Province, Pakistan.

Client

National Transmission and Dispatch Company Limited (NTDC)

Status

17% Completed

Read Complete Report

DESIGN, MANUFACTURE, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 132KV/11.5KV (GIS) GRID STATION DHA/EME-SECTOR LAHORE ON TURNKEY BASIS.

Project Detail

DESIGN, MANUFACTURE, SUPPLY, ERECTION, TESTING & COMMISSIONING OF 132KV/11.5KV (GIS) GRID STATION DHA/EME-SECTOR LAHORE ON TURNKEY BASIS.

Award Date: 29th May 2018

Commencement Date: 10th July 2018

Expected Completion Date: 9th July 2019

Location: Lahore, Pakistan

Client: Defence Housing Authority (DHA) Lahore

Percentage Completion: 26%

Read Complete Report

Tell Us

Global Exposure

Sustainability

  • Management Principals
  • Safety Management
  • Training
  • Ethical Management

Innovations

  • Research & Development
  • Intellectual Properties
  • Achievements
  • Certifications